THE NGO NETWORK ALLIANCE PROJECT - an online community for Zimbabwean activists  
 View archive by sector
 
 
    HOME THE PROJECT DIRECTORYJOINARCHIVESEARCH E:ACTIVISMBLOGSMSFREEDOM FONELINKS CONTACT US
 

 


Back to Index

City of Harare - Sewerage and Water Part 2
Councillor Michael Laban
February 16, 2003

Previous article

Hello

I am still waiting for some information from officials, but will continue with what I have, rather than wait any longer. The previous note on sewerage brought a fair amount of response, some from sewerage and water engineers. Some very interesting points raised, and I would like to get in touch with most of them because they undoubtedly know more than I do.

The second part of this sewerage and water story is about water. The City Department of Works has two divisions – the Planning Services Division, and the Engineering Services Division. Under the engineering Services Division, there are several branches, one of them being Sewerage and Farming, and another being Water. In some respects it is important that they remain separate, because the people and the equipment used for fixing sewerage pipes are not supposed to be the same people and equipment used for fixing water pipes, even though it is the same methods and equipment being used to fix pipes. Unfortunately, due to a shortage of everything, sewerage and water repair crews are often transported in the same vehicles.

One bad aspect of the branch separation is that when you say "water" they only talk about water. If you want to talk about the whole concept, and the fact that we are polluting our own water sources, you have to consciously make the distinction and talk about water and sewerage. It is a bit frustrating because each branch has their own problems and wants assistance with those problems.

I first had a meeting with Engineer Lovemore Mlanda, the Acting Deputy Chief Engineer. (Principle Engineer, Water Branch), and Bernard Chatukuta, who in 1997 became the Senior Engineer, and in 1998 was promoted to principle engineer and head of Water Section. Last week I visited Morton Jaffray with Mr Chatukuta and the Chief Chemist.

The Water Branch deals with the extracting, treatment and distribution of water.

Extraction Water comes from 4 water sources;

1. Harare Dam (formerly Henry Hallam)

2. Seke Dam (formerly Prince Edward) These two are 100 percent council owned. Water extracted from them is treated at the Prince Edward Works, which has a capacity of 90 megalitres a day, but only treats 65 megalitres.

3. Lake Chivero

4. Lake Manyame (formerly Darwendale) The city owns 83 percent of both these lakes. Water extracted from them is treated at Morton Jaffray, which has a capacity of 614 megalitres, but only treats 480 to 500 megalitres a day.

So we have a capacity to treat 704 megalitres a day, and an ability to treat between 545 and 565 megalitres a day (at this time).

Apparently, the projected demand for water, made in the mid to late 90s, was 700 megalitres a day by 2002. It was predicted, and now has happened - treated supply is below demand. If there are no rains this year, we will have to make do on less, because of the contamination of our sources of water. There is a Warning Statement from the SADC Drought Monitoring Centre from 12 December 2002. It would seem that both construction of more sewerage treatment capacity and/or another source of water supply (the second is the only option that the Water Branch wants to consider) are long-term solutions – i.e. up to five-year construction programmes.

The above Harare water sources supply Harare, Norton, Chitungwiza, Ruwa, Epworth, and Sublime Township. Through the Department of Water, Harare also supplies some major government establishments such as Nkomo Barracks, Elfrida Barracks and the ZDI, the Domboshawa Training Centre and Chikurubi Prison.

There are no estimates on how much of Harare’s water needs come from boreholes. None of the City’s supply is borehole water. There is likewise no information on how much effluent is treated through septic tanks, just the knowledge of which parts of the City have no sewerage reticulation system. For example, all Epworth sewerage is dealt with in local septic tanks, and does not flow into the City’s system.

Treatment
I will not get into this too deeply – my notes are not the best and it is quite technical. At Morton Jaffray, the raw water comes in from Chivero and Manyame to a mixing chamber, where activated charcoal is added. It then runs to clarifiers, where Aluminium Sulphate and Ecol 2000 are added (along with other chemicals as needed such as Sulphuric Acid to alter the PH to 6.3). The clarifiers take water in from the bottom, allow the algae and other substances to settle to a "blanket" towards the bottom, and cleaner water flows off the top. This water flows through filters, which are basically large sand beds. These are backwashed when they are full and are equipped with air blowers etc. to do this. The backwash should be transferred to the Otis Sludge Disposal plant. Water that goes through the filters has chlorine and lime added and is all mixed again. It goes to three sumps. From Sump 1, 3 small pumps send it to Lochinvar through 750 mm pipe. From Sump 2, pumps 4, 5 and 6 send it to Lochinvar and sometimes to Warren Control through 975 mm pipes. From Sump 3, pumps 7 to 14 send it to Warren Control through 2 x 1300 mm pipes.

There are two works at Morton Jaffray, the Old Works, opened in 1954, and the new works, opened in 1976. While the staff is dealing with very old facilities and a great deal of pressure, I found the attitude very disturbing. Everything seems to be done on a "minimum to get by" basis. Aluminium Sulphate comes by tanker truck daily and is pumped through hoses into tanks in a building. When I was there we had to climb over the hoses in the doorway, because they stayed that way all the time, since more was coming the next day. Various pipes delivering chemicals to the water streams were secured by twists of wire. To add the activated carbon, which comes in a large paper bag, a hosepipe is inserted into the bag, turned on, and the bag lain on the walkway grill. It then flows out of the bag and runs into the mixing tank below. When asked how long they had been using carbon, and how long they had been doing it like this, I was told "always". The officials say they have been asking for a pump to introduce the activated carbon properly since they started (1997-8 for some). The original works, however, did not have provision for this pump, so I can only conclude that sometime since 1976 the City started adding carbon to the water and no one has ever found the resources to get the equipment to do it properly.

Many more technical things looked wrong too, but I cannot really comment since I know so little. As a non-technical observer, many other things gave a bad impression. There were cobwebs everywhere – thick ones. The windows were dirty – very dirty. The grass was not cut. None perhaps vital to the efficient working of a water treatment plant, but things that give the impression that only the minimum has been done to avoid complete breakdown.

I made a deal with the officials there. If they could change their attitude and give a better impression of the works, I would do my bit to make Council and the people of Harare aware of the problems, and try to get them what was needed to make it work properly.

The Otis Sludge Plant (perhaps I have the name wrong) just sits there. In the Department of Works Report for 2000, it is said to be ready to be turned on, just waiting for the contractor to return from overseas. It has never been turned on. There is some dispute over payment or contracts, which has never been finalised, and so it sits. The Head of Water did not know any details – just the comment that "the Jews" had made it! Being very fond of Jews, but not at all fond of the Israeli government, I am interested to see what the real case is and who is involved.

Distribution
I am waiting for a map of the system, so forgive me if my notes are wrong, but the general impression is still the same.

Warren Control is obviously the biggest distribution works with 14 new pumps, and from there and Lochinvar water flows, usually by gravity to about 14 reservoirs around the city (those big concrete things you can sometimes see). Letombo and Alex Park are our two major reservoirs. Water from the Prince Edward Works enters the system in Hatfield, there are three main valves that are used to control flows and pressures, and several smaller pumping stations to take the water over higher ground (especially to the North East suburbs).

From what I understand, bad smelling water is usually a result of algae growth in the reservoirs, although some of it smelt bad (like fish) just after the filters at the works, before Chlorine was added. When there is a bad smell, it is often treated with Chlorine in the reservoir concerned.

The major problems outlined to me were the usual – funding. Water asked for $6.1 bn in the budget and was allocated $848 million for maintenance and upkeep. I hope they got more for new works, because an 11.4 megalitre reservoir costs $120 to $150 million to build. This is the same size as the Hatcliffe Reservoir. Highlands Reservoir is 61.74, and Greendale Reservoir is 70.79 megalitres. The officials also complain that there is too much bureaucracy in the procurement system.

I am told that we use more chemicals in the treatment of our water than any other municipality, and that Harare water is the cheapest of any municipality. If you look at water as a manufactured product, with raw water as the input, and the addition of power, labour, plant and chemicals to produce potable (drinkable) water as the outcome, then the cost of water should be based on that. However, there are only two things that the City charges us for – rates and water. (At least on a regular basis, dog and bicycle licenses etc are a minor thing). From those two things the City must also finance the provision (or failure to provide) of sewerage, clinics, libraries, rubbish collection, roads, administration, etc. etc. It is a difficult calculation but I am suspecting that the price of water should be increased up to ten times. That would make a huge political issue of an already over politicised utility.

Water Demand Management
WDM is a big issue these days. It stands for Water Demand Management, and has some fascinating aspects. Apparently, Bulawayo has kept water demand down to the levels they achieved during the 1992 drought. 2003 is the International Year of Fresh Water, and various organisations (and some individuals like myself) are involved in using it, and "Water Week" (17 to 22 March) to promote water issues at all levels. Environment Africa (specifically Thoko Ngwenya) is the secretariat. Both pollution/sewerage and WDM will be part of what I will be putting forward for our City, so I guess that is the next topic in my attempts to communicate with you all. Again, all comments are appreciated, even if I am not getting back to everyone and you think you are being ignored.

For more information, contact Cllr Laban by email at: mlaban@mango.zw

Please credit www.kubatana.net if you make use of material from this website. This work is licensed under a Creative Commons License unless stated otherwise.

TOP