|
Back to Index
Zim
to grapple with power cuts for the next five years
The
Standard (Zimbabwe)
August 25, 2013
http://www.thestandard.co.zw/2013/08/25/zim-to-grapple-with-power-cuts-for-the-next-five-years/
Zimbabweans
will have to grapple with power cuts for the next five years, until
the country completes new generation projects subject to availability
of funding, the power generating parastatal said last week.
This comes at
a time the power utility, Zesa, has intensified load-shedding as
generation capacity is way behind the rising demand, knocking off
the wheels of industrial revival.
In an update
last week, Zesa’s subsidiary, the Zimbabwe Power Company (ZPC),
said the current total generation capacity of 1 530MW was inadequate
to meet a demand of around 2 200MW.
ZPC generates
electricity at its five power stations located in Kariba, Hwange,
Munyati, Bulawayo and Hwange. The quintet has a combined installed
capacity of 1 960MW.
ZPC said the
power generation gap could be closed by new projects, which can
only be completed in four years’ time, once funding has been
secured. The power utility has been closing the gap through load-shedding
and imports from regional utilities.
“However,
because of severe electricity shortages in the region, we cannot
import more and ZPC power output will only increase after the generation
expansion projects have been completed by 2018 subject to availability
of funding,” it said.
ZPC said it
was facing challenges in raising adequate capital needed to maintain
the existing plant, as well as building more capacity.
ZPC said it
was working on electricity generation projects to close the gap
between demand and supply, through ensuring that the existing plants
operate at installed capacities and expanding Kariba and Hwange
power stations to add 900MW.
Only the hydro
project at Kariba is operating at installed capacity. Hwange Power
Station is operating at 70% of its capacity. The situation is dire
for the smaller thermal stations in Munyati, Bulawayo and Harare
whose capacities range from 20% to 33%.
The expansion
of Hwange and Kariba will cost an upward of US$1,6 billion.
In December,
ZPC and Chinese firm, Sino Hydro, signed a contract for the engineering,
procurement and construction of two units of 150MW each at Kariba
South Power Station. The cost is US$354 million.
“Financial
closure is expected to be reached by the end of September and the
construction period of the project from the date of commencement
is approximately 40 months,” ZPC said.
It said, the
addition of two units at Hwange Power Station would generate 600MW,
adding that construction would take four years from the date of
financial closure.
Please credit www.kubatana.net if you make use of material from this website.
This work is licensed under a Creative Commons License unless stated otherwise.
TOP
|