|
Back to Index
Press
statement by the Minister of Energy and Power Development initiatives
to boost the power situation
Elton Mangoma, Ministry of Energy
May 03, 2013
In view of the current
challenges besetting the efficient supply of power nationwide and the
need to enhance the financial position of the electricity utilities, the
Ministry of Energy and Power Development has come up with a number strategies
to mitigate the power situation in the country.
The measures being
taken are divided into Generation capacity and supply side activities,
Demand Side Management and Institutional changes. The supply side is further
split into short, medium and long-term measures.
The strategies include:
Status of
Generation
The generation capacity
of the Hwange Power Station has improved significantly with an average
of five units (580MW). This has allowed the Zimbabwe Power Company (ZPC)
to carry out upgrade works and preventive maintenance at the Kariba Power
Station without causing major power shortfall to the system. The Kariba
Power Station has continued to maintain a steady power generation.
Prepayment
Meters
The smart/prepayment
metering is a valuable short-term strategy which seeks to improve revenue
collection by the utility and influence behaviour change on how consumers
use electricity. The system also assists ZETDC to recover accrued debts
by deducting 20 percent on every electricity purchase going towards servicing
the debt, among other benefits.
As of yesterday, a
total of 150 000 prepayment meters had been installed for both domestic
and commercial users. Government issued a Statutory Instrument 44A on
Electricity (unpaid bills, prepaid meters and smart meters) regulations,
2013 which aims, among other things, to speed up the implementation of
the prepaid/ smart metering programme.
The Statutory Instrument
compels all electricity consumers to purchase and install smart meters
with the exception of high-density customers, rural customers and light
load agricultural customers. The Statutory Instrument also deals with
outstanding bills on the date on which the prepaid meter is installed
as these will be transferred to the property at which the prepaid meter
is installed.
In order to ensure efficiency, ZETDC this week commissioned a new Vending
Platform supplied by Itron of South Africa. The new Platform can accommodate
both smart and prepaid meters.
Medium Term
Power Generation
- Kariba South Expansion
- The Zimbabwe Power Company (ZPC) and Sinohydro have concluded negotiations
for the 300MW Kariba South Expansion Project. As a result, Sinohydro
has commenced work at the site.
- Hwange Power Station
- adjudication process for the 600MW Hwange Expansion Project has been
completed and the project was awarded to CMEC. Work is expected to commence
before the end of the year.
- 84MW Diesel Generator
- A diesel plant (84MW) that has operated for 100hours has been identified
at a capital cost of €37 million. This about 50% of the cost of
new plant. The ZPC has made a technical analysis and that diesel generators
are suitable for our system and have the capacity of reducing load shedding
by 80MW.
- 30MW Gairezi Small
Hydro Power Plant - The project is now at design stage following completion
of feasibility studies and official launch is expected this month.
- 500MW CBM Power
Station - ZPC has also floated a tender for resource mapping of coal
bed methane. The tender was awarded to WAPCOS of India and it is ready
to carry out the work. However, ZPC is awaiting CBM special grants documentation
from the Ministry of Mines and Mining Development. Instead there are
two grants awarded to one company Shangani Energy and another to China
Africa Sunlight by the mines ministry. The grants are overlapping with
the desired ZPC concession area. These concessions were granted after
Cabinet granted ZPC concession but the Mines and Mining Development
ministry is refusing to effect Cabinet decision.
- 1000MW Western
Area Power Station - China Railway International (CRI) and China International
Fund (CFI) have signed a Memoranda of Understanding (MoUs) with the
government to develop a 1000MW thermal plants. China Railway International
came for site investigation in December 2012 and has submitted a draft
contract for the project development. The finalisation of reinstating
the Western Area coal concession to the ZPC by the Ministry of Mines
is important. Again the Ministry of Mines and Mining Development is
not cooperating, causing a delay in the commencement of this project.
- 100MW On-Grid
Solar Power - Some suitable sites for the 100MW solar power plant are
being identified. The ZPC has engaged the Plumtree Town Council for
land to construct the power station. A tender for the 100MW power plant
is expected to be floated soon. The tender will cover BOT, IPP, PPP
and pure debt basis.
Long Term
Projects
- The Batoka Hydro
Electric Power Project - Zambia and Zimbabwe have agreed to undertake
this project on a BOT basis. This was after Zimbabwe agreed to honour
the EXCAPCO assets debt of $70.8 million. So far a total of US$40 million
has been paid towards the US$70, 8 million. The Zambezi River Authority
called for Expressions of Interest to develop the Batoka on a Build
Operate and Transfer basis. The response was extremely good -25 companies
showed interest and the majority from credible international organisations.
- The Great Imga
Hydro Project - is proposed on the Congo River in the DRC. This can
produce around 100 000MW. This project is too big for the DRC and requires
a regional approach. If this is constructed it will change the economic
fortunes of the region. Hydro power is cheap and it is worth the time
spent on promoting it.
Institutional
Changes
- Restructuring
of the power sector - The restructuring of ZESA Holdings has been approved
by Cabinet. This is to make ZESA more efficient and responsive to the
consumers, whilst at the same time, setting up a mechanism to make it
easy for Independent Power Producers to have a level playing field.
These developments
will result in the following:
- ZESA Holdings
be collapsed into a National Grid Services Company (NGSC) and move all
the legacy debts to this company. It will be 100% Government owned and
it will not be privatised. NGSC will be responsible for Transmission,
Market and Systems Operation. It will have the “reserve supply”
responsibility.
- ZETDC will transfer
the transmission functions to NGSC and transform to Zimbabwe Distribution
Company (ZEDC) and be responsible for Distribution of Electricity.
- Summary - Measures
to consolidate the power availability and reliability will continue.
Such measures will include taking out plant for preventive routine maintenance
and equipment upgrade. Negotiations for firm power imports from the
region will be pursued by both Government and the power utility. The
implementation of all power projects continue to be a critical success
factor for securing self-sufficiency and reliability in power supply
to the nation. To this end the Ministry is continuously evaluating project
risks and working on mitigatory measures to ensure the projects are
realised.
Please credit www.kubatana.net if you make use of material from this website.
This work is licensed under a Creative Commons License unless stated otherwise.
TOP
|