|
Back to Index
Statement by Minister Mangoma to Parliament on measures to improve
the power situation
Elton
Mangoma, Ministry of Energy
July 13, 2012
Mr Speaker Sir,
I have found it necessary to brief this House of elected representatives
on what we are doing in the Ministry to ease power outages in the
country.
Zimbabweans
across the country and in all spheres; from housewives to business
people, have a sad story to tell about the power cuts they experience
every day in their homes and in the factories.
Mr Speaker Sir,
it is the duty of government to explain the measures we are taking
to alleviate the plight of the people. The solution might not come
tomorrow, but the people of Zimbabwe deserve to know that we are
working flat out to mitigate the situation which deteriorated way
back due to non-investment in this critical sector. There was no
way we could resolve in three years a decay process that began decades
ago.
Nevertheless,
I rise to make public our efforts in redressing this national challenge.
It is a challenge
that has affected a cross section of people from the big corporates
in Harare and Bulawayo to clinics and health centres in Chendambuya
and Gokwe; from schools in Filabusi to the ordinary power consumers
in Budiriro and Pumula.
Mr Speaker Sir,
it is no laughing matter; but they say the most popular words in
Zimbabwe are "Magetsi auya." As government and as a
Ministry, we are aware of the mammoth task before us and we want
to assure you that we will discharge of our national duty to the
best of our ability.
1. INTRODUCTION
The power supply
in the country is inadequate leading to massive load shedding in
all the sectors. This is on the backdrop of:
i) No new generation
capacity having been created in the country since 1984.
ii) A serious shortage of capacity in the region because of increased
demand in their countries coupled with no new investment.
iii) Lack of maintenance, particularly from 1998 to 2009 leading
to serious degeneration of both Generation and Transmission and
Distribution infrastructure.
iv) Low and unviable tariff over the past decade (some correction
made in 2011).
v) Low funding from Treasury and high level of debtors.
vi) The economic revival has put pressure on the demand for electricity
and particularly on domestic consumers, who had absorbed the electricity
that was available from Industry and Mining.
2. MEASURES
BEING TAKEN
The measures
being taken are divided into Generation capacity and supply side
activities, Demand Side Management and Institutional changes. All
these will work towards alleviating load shedding and increasing
the power for enhanced economic activities. The supply side is further
split into short, medium and long term measures.
3. GENERATION
CAPACITY AND SUPPLY SIDE ACTIVITIES
3.1
Short term (900MW)
3.1.1
Optimisation of Hwange Power Station (250MW)
Mr Speaker Sir,
Hwange Power Station has an installed capacity of 950MW. It however
has been producing between 300 to 500 MW. This is a result of poor
maintenance, and lack of alignment of the production facility. For
example, the stage 2 turbines (generations) have a capacity to generate
220MW each, but the boilers are such that you can generate around
150MW. Improving the boilers can increase the capacity to 200MW
each. Work to identify what needs to be done is underway.
Poor maintenance
management is exemplified by the current saga on units 1 & 2,
where we had the rotors down and management concentrated on getting
them fixed without attending to ancillary equipment at the same
time. Now the rotors have been repaired, but work on the stator
only commenced last month. Measures are being put in place to avoid
such sloppiness including skills enhancement and greater team work.
3.1.2
Repowering Small Thermals (120MW)
All the small
thermals can produce, with constant coal supply 200MW, compared
to the current 60-80MW. Short term coal supplies can be increased
by more cooperation and minimal investment at Hwange Colliery Company
(HCC), so that they produce the required type of coal.
Immediate steps
are being taken to modify the boilers, so that they can use the
same thermal coal as Hwange Power Station. This is an 18month progamme.
ESSAR will lease Munyati Power Station and they have indicated that
they can make it produce 140MW.
3.2
Gairezi Hydro (30MW)
ZPC has applied
for a licence to construct the Gairezi hydro scheme. This is estimated
to cost $90m and the project will take 18-24 months. The licence
will be issued this month and finances are being arranged. It will
be necessary to work with OPC to avoid the delays of the State Procurement
Board (SPB).
3.3
Lupane Coal Bed Methane (500MW)
Mr Speaker Sir,
there is need to map and determine what resource there is in Lupane.
This is then followed with the construction of a gas fired plant
in Lupane. The first phase involves the drilling of exploratory
wells. As soon as these wells are drilled, instead of closing the
wells or flaring the gas, the gas will be directed to a series of
machines that generate between 5-10MW. These machines will be hired
from Agreko. It becomes possible to generate electricity almost
immediately the wells are drilled.
After mapping
and determination, a mining plan is then determined. The mining
plan is then executed taking into consideration the level of resource
and what it will be used for. The current proposed uses are electricity
generation and fertilizer production.
Mining can start
immediately after resource mapping with the gas from the Mining
wells also being directed to more hired machines. This term is called
Temporary Generation. These will only be removed after the commissioning
of the Permanent Plant.
There are 3
parties already interested in the resource mapping and determination
phase, who will do it on behalf of ZPC. Funding has already been
secured for this phase.
3.4
Solar Into Grid (100MW)
The main thing
that makes solar technology more expensive is the need to produce
and store during the day for use at night, when you can not produce.
The current situation is that electricity is short during the day
so there is no need to produce and store. Generating without storing
will bring the tariff to between 10c-12ckwh, which is within the
current tariff structure.
Solar plants
can be put up very quickly. Current discussions are centering on:
i) Should this
be one plant or a number of them.
ii) Signing of Power Purchase Agreement (PPA) to buy all the power
produced for a fixed period (consideration between 5-10 years).
The main issue
is acceptability of Zimbabwe Electricity Transmission and Distribution
Company as a party to the PPA.
3.5
Solar Panels on Homes
Mr Speaker Sir,
we have currently agreed with a housing cooperative in Mutare that
they put solar panels as part of their roofs. The electricity so
generated will be used within their homes and the surplus fed into
the grid. At night the homes will then be supplied by ZESA. At the
end of the month, the account will then be settled depending on
the power produced and consumed. The flow of electricity will be
measured using a Reverse Meter.
This policy
can be extended to anyone although it may be more applicable to
new housing complexes as the panels will be part of the cost of
the roof, and therefore no extra investment required.
3.6
Solar Lamps
There is a programme
under Rural Electrification Agency (REA) to produce solar lamps
locally targeted to retail at $10 or less. REA is working with local
industry to make sure there is significant value addition in this
project. It will then lead to localisation of technology and job
creation. Designs are at an advanced stage.
Treasury has
provided $1,5m to this project, which will enable particularly school
children to by these lamps in instalments. The lamps are earmarked
for rural schools. The involvement of industry means that a lot
more solar lamps can be produced for commercial purposes to be made
available to the generality of the public. These solar lamps are
a good source of lighting when the electricity goes out.
3.7
Imports
Mr Speaker Sir,
Zimbabwe used to import as much as 500MW firm power from SNEL, EDM,
HCB and ZESCO. At the moment the only firm power is 100MW from HCB.
The demand for electricity within the region has been growing, to
a point now where whatever can be produced is utilised. The likely
immediate source of imports is EDC and HCB. Negotiations are underway.
Botswana is
likely to commission a power plant soon. EDM is being persuaded
to export to us the power (50MW) they are currently exporting to
Botswana.
Zambia is likely
to commission Kariba North expansion next year and dialogue is taking
place now. Mozambique is planning to do Temporary Generation at
their Southern Gas fields and this will add additional generation.
We have registered our interest. Payments done to reduce our debt
make us worth considering.
4. DEMAND
SIDE MANAGEMENT
4.1
Prepaid Meters
The tender board
awarded tenders to:
i) Solahart Zimbabwe (Pvt) Ltd (Zim)
ii) Nyamezela Consulting Engineers cc (RSA)
iii) ZTE Corporation (China)
iv) Finmark Marketing (Pvt) Ltd (Zim)
These tenders
exclude Harare and Bulawayo, which are the two places with the greatest
need. The tenders are for supply and fix. Contracts signed are to
ensure that those who quickly install their meters are allowed to
install additional ones so as to roll out as quickly as possible
and not be held by laggards purely on the basis that they won a
tender. It is proposed to use the same tender winners on the same
performance basis for Harare and Bulawayo.
The roll out
is expected to start next month (June 2012) and be completed within
10 months. The current prepaid meter platform is being upgraded
to handle different types and increased number of meters.
Prepaid
Meter Platform Tender
Mr Speaker Sir,
a tender was floated, adjudicated and awarded to REVMA. The adjudication
process was fraudulent. All other tenderers who proposed external
hosting were disqualified as it was a specific requirement that
the platform be based at ZETDC. The adjudicators knew but presented
REVMA as a direct supplier until (the contract signing stage when
REVMA wanted to be paid 60 cents per transaction.
Discussions
with State Procurement Board (SPB) indicated that REVMA had not
misrepresented their position, but that the adjudicators had falsely
misrepresented the facts. As a result SPB could not reverse their
award. The only recourse is for ZETDC to approach the Administrative
Court for the nullification. ZETDC has now been directed to approach
the court. Any award must now be based on those who show on the
ground that they have a system that works.
4.2
Compact Florescent Lamps (CFLs)
The contract
for the supply of CFLs has finally been signed (21/05/12). It is
hoped that the first batch of 1 million lamps will be delivered
on 30 June 2012. Installation of the lamps will commence around
mid July.
The installation
of the 5,5 million lamps, estimated to be completed by October 2012,
will save evening peak electricity equivalent to 180MW.
4.3
Biogas
Mr Speaker Sir,
biogas is a sustainable, environmentally friendly sources of energy.
It is mostly used for heating and cooking purposes, and thereby
releasing electricity for other purposes.
A Zambian expert
has been engaged for the purposes of technology transfer through
the construction of prototype digesters. Three sites that have been
identified are:
i) Mbare Musika
- Vegetable market
ii) Harare Hospital
iii) Roosevelt Girls High School
There is need
to identify two other users covering:
a) Farm environment
b) Domestic dwelling.
The work on all these prototypes is expected to commence in June.
Local constructors
are expected to gain knowledge and insight into the construction
for future propagation. Treasury budgeted $1,5 million for this
purpose. The funds are sufficient to cover other educational and
health institutions in all the provinces. REA is the implementation
agent.
The residue
after the gas has been used is very good organic fertilizer. Local
industry is being involved in the manufacture/adaptation of gas
stoves. The cooking system at Harare Hospital will be completely
revamped.
5. MEDIUM
TERM
5.1
Hwange and Kariba Expansion Projects (900 MW)
Hwange (600MW) and Kariba (300MW) expansion projects are currently
being tendered for. The tenders are due to close on 5 June 2012.
(Been advised SPB moved closing date to 3 July 2012). There are
now four (4) tenderers for each project. The main issues to be considered
are:
i) The availability
of funding to carryout projects. An alternative plan to fund Kariba
South expansion has reached an advance stage.
ii) The technology to be used to create the cavity at Kariba -
the type of blasting/drilling - due to the weak rock formation.
iii) The Ministry
of Finance had written advising abandoning the tender process at
Kariba in favour of Sino hydro, following the agreement they signed
with China. It is recommended to carry through with the tender as
scrapping it now could cause legal complications and further delay
the project.
The projects
are expected to take around 48 months.
5.2
Hwange-Western Areas (1000MW)
Mr Speaker Sir,
this is a new project that will result in the construction of a
coal fired power station in the Western Areas Coal fields. The Western
areas coal fields concession was granted to ZPC by Cabinet in July
2010 for the purposes of attracting investors into power generation.
Promising negotiations
are underway with China Railways International (CRI). The main issues
are:
i) That the power plant will belong to ZPC 100%.
ii) That a mining venture is formed between ZPC and CRI
iii) CRI will operate the power plant for the benefit of ZPC until
the loan has been repaid.
It is estimated
that the power plant will take around 3-4 years to construct, after
a 6-12 month period of surveying and designing.
5.3
Independent Power Producers (IPPs)
A number of
IPPs have been licensed. The three big projects are Sengwa (2400MW)
Lusulu(2000MW) and ESSAR (600MW).
6. LONG TERM
6.1
Bindura Gas Plant (2200MW)
Mozambique has
discovered vast natural gas quantities in the Rovuma Basin. We have
expressed our interest to have access to the natural gas.
The idea is
to pipe the gas from Rovuma Basin, through the bridge at Tete to
Bindura. A gas fired power station is then constructed in Bindura
and feed into the Bindura-Songo transmission lines. (This is similar
to what Ghana has done with the Nigerian Gas).
The gas pipeline
then extends to Harare, where it will be piped to the residential
areas for cooking purposes, (like in most of the developed countries).
(This whole plan can be replaced by the Lupane CBM depending on
the quantum of the resource).
6.2
Batoka (800MW)
Mr Speaker Sir,
Zambia and Zimbabwe agreed on 10 February 2012 to embark on the
Batoka hydro project with a total capacity of 1600-2000MW. It was
agreed to proceed on a BOT basis under the leadership of the Zambezi
River Authority (ZRA). Zimbabwe agreed to pay Zambia $70.8million
for the CAPCO assets. $10m has since been paid. Interest has been
agreed at $114m and there is no repayment plan. Zimbabwe has already
asked Zambia for interest not to be paid.
A detailed geological
survey was done in 1994. It may be necessary to carry out some confirmatory
geological survey, together with an Environmental Impact Assessment.
It is envisaged
that the ZRA in consultation with the two countries will finalise
the BOT framework soon so that they call for interested parties
to put forward their proposals. The main issues to be considered
are the legal and commercial issues and leave room for the interested
parties to compete on issues like design and technology.
6.3
The Great Inga
The Great Inga
hydro project is proposed on the Congo River in the DRC. This can
produce upwards of 40000MW. This project is too big for the DRC
and requires a regional approach. If this is constructed it will
change the economic fortunes of the region. It requires strong leadership
and project design skills to make all the political leaders comfortable
with the project. Hydro power is cheap and it is worth the time
spent on promoting it.
7. OTHER
INSTITUTIONAL ISSUES
7.1
Funding
Mr Speaker Sir,
the funding of ZESA by Treasury has been minimal, despite the provisions
that have been made in the budget. A verbal agreement has been reached
with the Minister of Finance to deduct the subsidy to Sable Chemicals
and Government's indebtedness to ZESA against the funds paid
by Treasury.
The Zimfund
promised some $30m as urgent intervention. This money was paid in
by the Donor countries almost a year ago. No disbursements have
been made yet.
7.2
Restructuring of ZESA
Mr Speaker Sir,
it is proposed to restructure ZESA to make it more efficient and
responsive to the consumers, whilst at the same time, setting up
a mechanism, which will make it easy for Independent Power Producers
have a level playing field. ZESA Holdings was supposed to be only
an instrument of holding shares in the successor companies. Instead
it morphed into a huge bureaucracy negating the very point of establishing
successor companies. In 2002 the Transmission business was legislated
to be separate from distribution, only to be reversed later.
It is proposed
that:
i) ZESA Holdings
be collapsed into a National Grid Services Company (NGSC) and move
all the legacy debts to this company. It will be 100% Government
owned and it will not be privatised. NGSC will be responsible for
Transmission, Market and Systems Operation. It will have the "reserve
supply" responsibility.
ii) ZETDC will
transform to Zimbabwe Distribution Company (ZDC) and be responsible
for Distribution of Electricity.
iii) Each of
the companies will have a separate Board which will report directly
to the shareholder.
These companies
will be:
- Zimbabwe
Power Company (ZPC)
- Zimbabwe
Distribution Company (ZDC)
- National
Grid Services Company (NGSC)
- ZESA Enterprises
(Pvt) Ltd (ZENT)
- Powertel
7.3
Establishing an Electricity Industry
Almost 90% of
all the spares and services to ZESA are from outside our borders.
There is no doubt that the engineering capacity at Independence
was so high and yet we are not reviving it. Local content of Hwange
Power Station was over 50%. ZESA has been a major consumer and the
spending power it has can be used as a catalyst for the revival
of the local electricity industry. On top of this, our own engineers
have excelled in the region and beyond.
Mr Speaker Sir,
this requires deliberate targeting and formation of partnerships.
ZENT has been improving its manufacturing capacity, for example,
they now can produce 500 transformers per month. We can therefore
not allow transformers from outside at the expense of knocking out
this capacity. In the same vein, ZPC organised a workshop with the
local industry so that they can hold each other's hands as
they build the industry together. This requires flexibility in the
rules of the SPB.
The projects
listed under IPP indicate that even if a quarter of them are realised,
it is a lot of work. This is the time to ensure that the capacity
is here to tap and localise the investment resource whilst at the
same time creating the much needed jobs.
Creating local
capacity will also reduce the time it takes to carryout repairs.
For instance, generator 3 at Harare Power Station has been out for
more than a year, with the rotor alignment waiting for its turn
in South Africa. We need to empower our people by making them partners
in the supply of services and spares.
8. POLICY
DOCUMENT LAUNCH
In early 2010,
Cabinet approved the Energy Policy document. Over this period series
of workshops have been held with stakeholders in order to refine
the policy and prepare for implementation. The product of those
consultations has been completed, thanks to the assistance by UNDP.
It is planned
to launch the document in July.
- Zimbabwe
Power Company (ZPC)
- Zimbabwe
Distribution Company (ZDC)
- Grid Services
Company (NGSC)
- ZESA Enterprises
(Pvt) Ltd (ZENT)
- Powertel
7.3
Establishing an Electricity Industry
Almost 90% of
all the spares and services to ZESA are from outside our borders.
There is no doubt that the engineering capacity at Independence
was so high and yet we are not reviving it. Local content of Hwange
Power Station was over 50%. ZESA has been a major consumer and the
spending power it has can be used as a catalyst for the revival
of the local electricity industry. On top of this, our own engineers
have excelled in the region and beyond.
Mr Speaker Sir,
this requires deliberate targeting and formation of partnerships.
ZENT has been improving its manufacturing capacity, for example,
they now can produce 500 transformers per month. We can therefore
not allow transformers from outside at the expense of knocking out
this capacity. In the same vein, ZPC organised a workshop with the
local industry so that they can hold each other's hands as
they build the industry together. This requires flexibility in the
rules of the SPB.
The projects
listed under IPP indicate that even if a quarter of them are realised,
it is a lot of work. This is the time to ensure that the capacity
is here to tap and localise the investment resource whilst at the
same time creating the much needed jobs.
Creating local
capacity will also reduce the time it takes to carryout repairs.
For instance, generator 3 at Harare Power Station has been out for
more than a year, with the rotor alignment waiting for its turn
in South Africa. We need to empower our people by making them partners
in the supply of services and spares.
8. POLICY
DOCUMENT LAUNCH
In early 2010,
Cabinet approved the Energy Policy document. Over this period series
of workshops have been held with stakeholders in order to refine
the policy and prepare for implementation. The product of those
consultations has been completed, thanks to the assistance by UNDP.
It is planned
to launch the document in July.
Conclusion
Mr Speaker Sir,
I wish to assure the House
that we are aware of the plight facing the people of Zimbabwe. We
share with them the grief and misery of not having a reliable power
supply.
I pledge to
be making these ministerial statements to update the public on the
progress in instituting these measures.
We owe it to
the people of Zimbabwe.
I Thank You
Please credit www.kubatana.net if you make use of material from this website.
This work is licensed under a Creative Commons License unless stated otherwise.
TOP
|